Environmental mitigation, impact on traffic and approach to consultation among Lower Thames Crossing DCO issues


Lower Thames Crossing... the saga rumbles on

We reported last week that Highways England had withdrawn its application for a Development Consent Order to build the Lower Thames Crossing.
Now we have been updated by HE on the issues relating to the Planning Inspectorate and the likely way forward.
A message to  stakeholders said: “… we’ve now had further dialogue with the Planning Inspectorate about their expectations around our application.
“The fundamentals of the Lower Thames Crossing, including its objectives and location, will remain the same but we will further develop some technical information related to some elements of the scheme before we resubmit our application next year.
“The feedback from the Planning Inspectorate includes requests for:
“Further information on the impact of the project on traffic during the construction phase. We recognise that stakeholders are keen to find out more information about our construction traffic appraisals and will be engaging with them on these issues.
“Further assessments about how an existing jetty on the River Thames near the northern tunnel entrance construction site could potentially be used during the construction phase. The operation of the jetty could, if used, impact river traffic. We will be developing Navigational Impact Assessment and engaging with stakeholders on this topic.
“More details on our approach for managing materials and waste, including how the different contractors will coordinate the reusing, recycling or disposal of waste.
“An enhanced Habitats Regulations Assessment to provide a more detailed explanation of our approach to assessment of potential effects on European designated sites where we have indicated there would be no likely significant effects as a result of the construction and operation of the new road alone, or in combination with other projects.
“More detail on our approach to the long-term management of the project’s proposed environmental mitigation.
“The Planning Inspectorate has also shared some feedback from Local Authorities on our approach to consultation. We will consider this feedback carefully as we refine key areas of our submission ahead of resubmitting our application for a Development Consent Order.
“For a project of the size and complexity of the Lower Thames Crossing, it is reasonable for the Planning Inspectorate to ask for further information, and we are doing everything we can to resubmit our application at the earliest opportunity.”